Evolving Skatepark
Our projects › Dordogne (24)

Vergt (24)

Pumptrack

Client
Vergt Town Council
Brief
Pumptrack
Our appointment
Project management, joint contractor
Team
Atelier du Sillon (lead), Evolving Skatepark (joint contractor)
Riding surface
Pumptrack: 730m² of asphalt
Total site area
2180 m²
Cost of works
€141,000 excl. VAT
Whole scheme: €380,000 excl. VAT
Design studies
December 2022 to April 2023
Works
September 2024 to October 2024
Delivery
October 2024
Disciplines
Skateboarding, inline, scooter, BMX
Pumptrack in Vergt
Pumptrack in Vergt — view 2Pumptrack in Vergt — view 3Pumptrack in Vergt — view 4Pumptrack in Vergt — view 5Pumptrack in Vergt — view 6Pumptrack in Vergt — view 7
The project

Pumptrack in Vergt

Project management appointment for the construction of a pumptrack.

The pumptrack forms part of a wider park scheme by Atelier du Sillon, intended to create a leisure space for all generations. It sits beside the existing multi-sports court, in a large meadow.

What sets this project apart is that the embankments were extended so a children's play area could sit alongside.

Pumptrack opened in 2025.

The project team

Qui a fait quoi

RoleParty
Team leadAtelier du Sillon
ContractorsWest pump
Design & project managementEvolving Skatepark (lead, with Atelier du Sillon)
Réalisation pumptrackWest Pump