Evolving Skatepark
Our projects › Charente-Maritime (17)

Rochefort (17)

Action sports complex: streetpark, open bowl, beginners' area and pumptrack

Client
Rochefort Town Council
Brief
Action sports complex: streetpark, open bowl, beginners' area and pumptrack
Our appointment
Project management, joint contractor
Team
Fabien Charlot Paysagiste, Evolving Skatepark
Riding surface
Pumptrack length: 700m²
Streetpark and bowl area: 800m²
Beginners' area: 300m²
Total site area
3000 m²
Cost of works
€430,000 excl. VAT
Delivery
2022
Disciplines
Skateboarding, inline, scooter, BMX
Action sports complex in Rochefort
Action sports complex in Rochefort — view 2Action sports complex in Rochefort — view 3Action sports complex in Rochefort — view 4Action sports complex in Rochefort — view 5Action sports complex in Rochefort — view 6Action sports complex in Rochefort — view 7
The project

Action sports complex in Rochefort

Project management appointment for an urban action sports complex in three phases: first a streetpark and an open bowl built in 2017, then a beginners' area in 2021 and a pumptrack in 2022.

Three phases: beginners' street area €95,000 (2020), pumptrack €135,000 (2022), streetpark and bowl €200,000.

Skatepark opened in 2022.

The project team

Qui a fait quoi

RoleParty
Team leadF. Charlot paysagiste
ContractorsPump: Htracks · Learner street: IO Skateparks · Street and bowl: Concrete Flow ·
Design & project managementEvolving Skatepark (lead, with Fabien Charlot Paysagiste)
Streetpark & open bowl constructionConcrete flow
Réalisation aire initiationIO Skateparks
Réalisation pumptrackHtracks
Let's talk

A comparable project in your town?

The first conversation costs nothing and often clears up a great deal.