Evolving Skatepark
Our projects › Gers (32)

L'Isle-Jourdain (32)

Streetpark and concrete ramp

Client
L’Isle-Jourdain Town Council
Brief
Streetpark and concrete ramp
Our appointment
Project management, joint contractor
Team
Fabien Charlot Paysagiste, Evolving Skatepark
Riding surface
Skatepark area: 500m²
Total site area
900 m²
Cost of works
€150,000 excl. VAT
Design studies
July 2019 to September 2019
Works
Octobre 2019 à Février 2020
Delivery
February 2020
Disciplines
Skateboarding, inline, scooter, BMX
Skatepark in L'Isle-Jourdain
Skatepark in L'Isle-Jourdain — view 2Skatepark in L'Isle-Jourdain — view 3Skatepark in L'Isle-Jourdain — view 4Skatepark in L'Isle-Jourdain — view 5Skatepark in L'Isle-Jourdain — view 6
The project

Skatepark in L'Isle-Jourdain

The L'Isle-Jourdain skatepark, at the leisure park, covers 500 m² and is built entirely in concrete. It offers a 1.70 m ramp with a 2 m extension, a half-pyramid, a funbox, ledges, curbs, rails and banks, suited to skateboard, BMX, skates and freestyle scooter. Free and open all year, it stands on Avenue du Bataillon de l'Armagnac, a step from the lake. Funded through a participatory budget, it is regarded as one of the best skateparks in the Gers.

Skatepark opened in 2020.

The project team

Qui a fait quoi

RoleParty
Team leadF. Charlot paysagiste
ContractorsColas
Design & project managementEvolving Skatepark (lead, with Fabien Charlot Paysagiste)
Réalisation StreetparkColas
Let's talk

A comparable project in your town?

The first conversation costs nothing and often clears up a great deal.